Unit commitment (UC) captures the fact that thermal power plants cannot be switched on and off freely. Starting a unit has a cost, and once running, a plant must typically stay on, above a minimum output, for a minimum period before it can shut down again. Without UC, a dispatch model can turn a coal plant fully on and off every hour at no cost, which overstates the flexibility of a thermal fleet and understates the value of storage and flexible generation. To use unit commitment, mark thermal technologies as committable. The model then tracks a binary on/off (commitment) status for each committable unit at every hour, and accounts for start-up costs, shut-down costs, and minimum up/down times.
Unit commitment applies to single-year dispatch (PyPSA) scenarios. Marking any technology as committable turns the problem into a mixed-integer linear program (MILP). This is more realistic, but slower to solve than a linear dispatch (LP).

When the model uses unit commitment

Unit commitment is opt-in per technology:
  • If no technology is committable, the scenario solves as a linear dispatch (LP).
  • If any technology is committable, the scenario solves as a MILP, with commitment decisions co-optimised alongside dispatch.
See Model frameworks for the distinction between dispatch and capacity expansion.

Setting up unit commitment

Set up unit commitment with AMP. Ask AMP to duplicate your dispatch scenario and enable unit commitment on the thermal technologies. It will present the result for your review before you run it. If you also need capacity expansion first, ask AMP to soft-link a solved capacity-expansion scenario (see soft-linking with AMP).
1

Start from a dispatch scenario

Create or duplicate a draft single-year dispatch scenario for the year and country you want to study. Only draft scenarios can be edited. If you also want to optimise capacities, do that first in a separate capacity-expansion run (see Unit commitment and capacity expansion below).
2

Enable unit commitment

Using the inputs grid CSV template, set Committable to 1 for each technology you want to commit (see valid technologies below), then set its Start-up cost, Shut-down cost, Minimum up time, and Minimum down time. Optionally set Up time before / Down time before to describe the unit’s state immediately before the modelled horizon.
3

Check the minimum stable generation (optional)

Each valid technology has a default Minimum stable generation, so enabling Committable is enough for unit commitment to take effect. Override it where you have better data for a technology (see Minimum stable generation below).
4

Confirm capacity is fixed

Check each committable technology is not capacity-expandable (Maximum additional capacity set to 0). See Unit commitment and capacity expansion below.
5

Run and compare

Solve the scenario, then compare it against the same scenario with Committable off (the LP equivalent). The unit-commitment run should show fewer, longer thermal on/off cycles and the associated start-up costs.

Parameters

Committable is the master switch and is off by default. The other seven parameters are only applied to a technology once it is committable.
Start-up and shut-down costs are entered per MW of the unit’s capacity (USD/MW); the model converts them to an absolute cost per start using the unit’s capacity. Times are entered in whole hours.
If Up time before isn’t set, the unit is assumed to have been online for one hour before the horizon. With a Minimum up time set, this holds the unit on for the first hours of the horizon (the Minimum up time minus one hour). If you set Down time before, also set Up time before to 0; otherwise the unit is held both on and off at the start, and the scenario is infeasible.
Run unit-commitment scenarios at hourly (high) temporal resolution. The minimum up/down times (in hours) and the per-start costs are only represented accurately when each timestep is one hour; at coarser time-slice resolutions they are inaccurate.

Valid technologies

Unit commitment is meaningful only for generators that have significant start-up costs and minimum run times. It can be enabled for four technology groups, including their variants:
  • Thermal — coal, gas and oil plants
  • Bioenergy — including biomass and biogas
  • Carbon capture and storage
  • Nuclear — often run as must-run in practice; see Interaction with Minimum hourly utilisation for how to keep a unit running
See the technology directory for the variants in each group. Renewables, hydro, storage, and network technologies (transmission, interconnection) cannot use unit commitment. Their operation is limited by other factors, such as weather, reservoir levels and state of charge.

Minimum stable generation

Minimum stable generation is the lowest output a committable unit can run at, as a proportion of its capacity. It is a single value per year, and is only applied when the technology is committable. Each valid technology has a default value, so enabling Committable is enough for unit commitment to take effect. Override it where you have better data. In practice, unit commitment only changes the dispatch when a committable unit has a minimum output above zero:
  • Without unit commitment, a minimum output is a hard floor the plant must meet in every hour.
  • With unit commitment, the floor only applies when the unit is committed: the plant can either run at or above it, or shut down entirely.
If a committable unit’s minimum output is 0 (Minimum stable generation is 0 and Minimum hourly utilisation isn’t set), it can stay committed at zero output at no cost, so the model has no reason to shut it down: no start-up or shut-down events occur, and enabling Committable only makes the model slower (a MILP) without changing the dispatch.

Interaction with Minimum hourly utilisation

Minimum hourly utilisation sets a minimum output for individual hours. Where both are set for a technology, Minimum hourly utilisation takes precedence in those hours and Minimum stable generation applies in the rest. For a committable technology, both behave the same way: each sets the minimum output when the unit is committed.
Under unit commitment, neither parameter can force a unit to run. Both only apply in hours where the model has chosen to commit the unit, and the model can always shut it down instead. In particular:
  • Fixing a technology’s output to historical hourly levels with Minimum hourly utilisation only holds if the technology is not committable.
  • To keep a unit running in every hour (must-run), leave it non-committable and set its Minimum hourly utilisation.
  • To guarantee a unit produces a minimum amount of energy over the year, use Minimum annual utilisation. The model then chooses which hours to run it.

Unit commitment and capacity expansion

A committable technology must have a fixed capacity: it cannot also be capacity-expandable in the same scenario. (Start-up costs are applied per MW of the unit’s capacity, which is only well-defined when that capacity is fixed.) If a technology is both committable and capacity-expandable, the run fails with an error. To study unit commitment on a system whose capacities you also want to optimise, use the two-run soft-linking workflow:
  1. Run a capacity-expansion scenario (OSeMOSYS, or PyPSA with capacity expansion) to determine the capacity mix.
  2. Create a dispatch scenario for the year of interest with those capacities fixed (set Maximum additional capacity to 0), and enable unit commitment there.
See Setting up unit commitment above. AMP can run this workflow for you.

Interpreting the results

For every committable unit, a unit-commitment scenario reports:
  • Unit commitment status — the binary on/off state of the unit in each hour. Note this is commitment, not output: a committed unit can still produce zero if its minimum output is 0.
  • Start-up and shut-down events — where the status switches on (start-up) or off (shut-down).
  • Start-up and shut-down costs — the total cost of those events, reported separately and already included in the total system cost.
See Viewing results for where to find these outputs. AMP can also help diagnose an infeasible unit-commitment run.

Performance

Because unit commitment makes the model a MILP, solve times are longer than for the equivalent LP dispatch, and scale with the number of committable units and the number of hours. Very large unit-commitment scenarios may exceed platform size limits or run-time limits.
If the solver does not find an optimal solution within the time limit, the run fails rather than returning a usable near-optimal result. If this happens, try reducing the number of committable technologies or nodes. See Run statuses for what to do next.

Common infeasibility causes

  • A unit held on or off at the start of the horizon — Up time before and Down time before set the unit’s state before the horizon, and a Minimum up or down time then holds it in that state for the first hours. The scenario is infeasible if this conflicts with demand, or if both are set so that the unit is held on and off at once (see Parameters).
  • Conflicting operational constraints — for example a Minimum annual utilisation that forces a committable unit to run in a way its start-up/shut-down and minimum-time constraints cannot satisfy. Review annual utilisation constraints on committable technologies when enabling unit commitment.
See Infeasibilities for how to diagnose these.